Overview

New York University is scheduled to complete a window replacement project at 75 Third Avenue, Third North Residence Hall. The project is scheduled to begin in mid-April 2021 and continue until August 2021.

Work Hours

  • Monday - Friday
    9:00 am - 5:00 pm
  • Weekend work may be required, neighbors will be given advance notice.

Current Project Update

April 22, 2021

  • Installation of the sidewalk bridge has been rescheduled for Tuesday, April 27. The operation is scheduled to take between 5-6 days.

Scope of Work

  • This project includes the replacement of the existing windows and associated components.
  • Sidewalk bridging will be erected around the perimeter of the building for pedestrian safety.
  • An enclosure will be constructed on East 12th Street and 3rd Avenue to store materials and equipment. A fork lift will be used to dismount windows.
  • Materials will be delivered and removed through the north entrance.
  • Work will be phased, beginning with the south tower.
  • As with any active construction site, dust will be generated in the area immediately surrounding the work and noise will be generated by mechanical equipment and hand held tools. 