Overview

NYU is completing a sidewalk vault repair project at 20 Cooper Square. This will include demolition of the existing sidewalk and pouring of a new sidewalk. The project is scheduled to begin in mid-May and continue until July 2020.

 

 

 

Work Hours

  • Work hours are Monday - Friday 7:00am - 4:00pm.
  • Night and weekend work may be required. Neighbors will be given advance notice of night or weekend work.


Current Project Update

June 11, 2020

Contractors are scheduled to work on Saturday, June 13. Work hours are 8:00am-4:30pm.

Scope of Work

  • This project consists of demolition, vault repairs, and pouring of a new sidewalk.
  • A concrete truck will be onsite during the pouring stage of the project.
  • As with any active construction site, dust will be generated in the area immediately surrounding the work and noise will be generated by mechanical equipment such as jackhammers and hand held tools.  

Stay Connected