NEWS & UPDATES

Homepage News & Updates
Washington Mews
April 16, 2012

Streetscape work restoring Belgian blocks and cobblestones is scheduled for three consecutive Saturdays: April 14, April 21, and April 28, 2012, from 9AM to 5PM. Noise will be minimal.
Read more »

Basic Science
April 5, 2012

The perimeter fencing at 433 1st Ave. is now fully erect. Regularly scheduled work continues at the site. Read more »

Basic Science
February 22, 2012

Weekend work will be required for re-striping the bicycle and traffic lanes on First Avenue. Read more »

Washington Mews
January 20, 2012

Due to city regulations and Department of Environmental Protection (DEP) requirements, work on the watermain vault and is anticipated to continue beginning Monday, January 23, 2012. Read more »

Washington Mews
December 22, 2011

Work on the Water Main vault is anticipated to resume the first week of January. Read more »

Washington Mews
November 23, 2011

Work continues on the watermain vault and the renovation of 14A Mews continues. Read more »

OTHER PROJECTS

Maintaining Our Facilities - Local Law 11

Local Law 11 work is mandated by the City of New York and requires all buildings six floors or higher to be inspected and repaired on a regularly scheduled basis.

29 Washington Place - Brown Building

To comply with NYC's Local Law 11, we will begin façade repairs at the Brown Building at 29 Washington Place.

  • The sidewalk shed will extend 20 feet beyond the building's boundaries along Washington Place and Greene Streets.
  • This work will be happening concurrently with the Local Law work at the neighboring Silver Center.
  • Preparation for this project will begin in late May 2011 and the work is projected to be completed in August 2011.

35 Fifth Avenue - Rubin Residence Hall

To comply with NYC's Local Law 11, masonry repairs are scheduled at Rubin Residence Hall at 35 Fifth Avenue.

  • A sidewalk bridge will be installed adjacent to the building. The sidewalks will remain open at all times during the project.
  • Once the masonry repairs are complete the sidewalk bridges will be removed.
  • The project began at the end of May 2011 and is projected to be completed in August of 2011.

75 Third Avenue - Third Avenue North Residence Hall

To comply with NYC's Local Law 11, masonry repairs are scheduled at Rubin Residence Hall at Third Avenue North Residence Hall at 75 Third Avenue.

  • A sidewalk bridge will be installed adjacent to the building. The sidewalks will remain open at all times during the project.
  • Once the masonry repairs are complete the sidewalk bridges will be removed.
  • The project began at the end of May 2011 and is projected to be completed in August of 2011.