Skip to Navigation | Skip to Content

CURRENT PROJECT

58 Washington Square South - Center for Academic and Spiritual Life

ANNOUNCEMENTS

58 WSS - Catholic Center
Sidewalk
February 10, 2012

Pending permit approval, work on the sidewalk catch basins is scheduled to begin. Work in the interior of the building continues.

Construction Continues
December 16, 2011

Work continues throughout the exterior and interior of the building.

Sidewalk Renovation
November 4, 2011

As per New York City requirements, sidewalk renovation around the perimeter of the building is scheduled to begin on Monday, November 7, 2011. Sidewalk renovation is expected to take approximately 4 to 5 weeks to complete. Pedestrian traffic will be allowed with appropriate safety barriers.

Project Update
October 21, 2011

All sidewalks along the perimeter of 58WSS will remain closed due to the digging of catch basins and the repairing of the sidewalk. Pedestrian traffic will be re-routed to the North side of Washington Square South and the South side of West 3rd street.

The sidewalk on the west side of Thompson Street will remain open at all times. The sidewalks are expected to reopen by the end of November.

Lifts On Site
September 30, 2011

Work continues throughout the exterior and interior of the building. Two lifts will be on site starting the week of October 3, 2011. The lifts will be used to paint the exterior and install exterior trim. In addition, workers will be digging for catch basins for the building. This work should take approximately 3 weeks to complete.

Thompson Street Closure
September 2, 2011

A crane is scheduled to be brought on site on Tuesday, September 6, 2011. During this time, Thompson Street between Washington Square South and West 3rd Street will be closed, during construction hours (7AM to 6PM), to vehicular traffic and will remain open to pedestrian traffic along the west sidewalk.

The crane is expected to remain on Thompson Street for approximately 4 to 5 business days.

Project Update
August 5, 2011

Work continues throughout the exterior and interior of the building.

Project Update
May 31, 2011

Construction work continues throughout the exterior and interior of the building.

Project Update
March 25, 2011

Construction work continues throughout the façade and the interior of 58 Washington Square South.

Crane Update
February 23, 2011

The crane is now scheduled to be brought on site Monday, February 23, 2011.

Project Update
February 18, 2011

A crane is scheduled to be brought on site as preparations are made for work on the façade. Thompson Street between Washington Square South and West 3rd Street will continue to remain closed, but will remain open to pedestrian traffic along the west sidewalk. The crane is expected to remain on site until construction of the façade is finished.

Project Update
February 4, 2011

Construction work continues throughout the façade and the interior of 58 Washington Square South.

Project Update
January 10, 2011

Work on the façade and construction of the interior continues. This stage of the construction is expected to continue into spring 2011.

Project Update
December 2, 2010

The steel framing around 58 Washington Square South is now complete and work on the façade will continue into the early spring of 2011. Construction in the interior of the structure will also start this month.

Thompson Street will remain closed to traffic during this phase of construction between the hours of 7:00 AM and 4:00 PM Monday through Friday. Flagmen will remain positioned at the corner of Thompson Street and Washington Square South to guide pedestrian and vehicular traffic. The street will reopen after the workday and will remain open during the weekend.

Project Update
October 10, 2010

There will continue to be regular concrete pours for the next few weeks. Currently, the sub-cellar, cellar, first and second floor have been poured.

Next week, pouring will begin on the third and fourth floor and then continue up to top floor over the coming weeks. They have also started installing some of the piping in the lower levels.

The hoist has been installed and will be operating on the site.

In mid-November a crane will be brought back on the site for additional lifts and remain on the site for the balance of construction.

Crane Change & Concrete for Floors
September 17, 2010

All of the structural steel has been installed. As a result, the current crane that had been used to erect the steel will now be removed and replaced with a different crane that will remain on site for the next few months.

There will be increased activity on the site over the next few days as the construction team begins pouring concrete for the floors. They will begin with the sub-cellar level and work their way up the building.

Kimmel Center Water Shut Down
August 12, 2010

In order to accommodate the future sub-cellar break through between the Kimmel Center and the new 58 Washington Square South building, plumbing pipes are required to be relocated at the Kimmel Center.

A complete water shutdown is scheduled to start on Friday, August 13, 2010 at 11PM at the Kimmel Center. The required piping relocation will take place on Saturday, August 14, 2010.

Work is expected to be completed and the system re-energized by Sunday, August 15, 2010.

New Crane On Site
August 5, 2010

The steel installation has started. Currently the steel for the basement and first floor are complete with the second floor pillars being installed this week. A new crane is scheduled to be brought on site Friday, August 6, 2010 that is slightly smaller than the current one, and it will remain on site for the balance of construction.

Steel installation will continue into September.

Steel Installation
July 26, 2010

Steel installation has begun at 58WSS. During this time, Thompson Street between Washington Square South and West 3rd Street will be closed only during construction hours to vehicular traffic, but will remain open to pedestrian traffic along the west sidewalk.

A crane will be delivered in the next few weeks and remain on Thompson Street until all the steel is in place and the structure is built.

Project Update
July 1, 2010

Activity will begin to pick up as the first phase of construction ends and Phase II begins. Foundation work will be complete within the next few work days. Mobilization for Phase II will begin the week of July 12, 2010.

During this time, Thompson Street will be temporarily closed during construction hours. The street closure is necessary for the crane that will be used during steel installation. At the end of the work day the street will reopen for traffic. The construction crew will begin installing steel on the north end of the site working south. The sidewalk on the west side of the street will remain open at all times. Additionally, there will be a sidewalk bridge installed on the north side of West 3rd Street behind the construction site. A pedestrian walkway will remain open at all times.

There will be work on Saturday, July 3, 2010.

There will be no work on Sunday, July 5 or Monday, July 6, 2010 in observance of Independence Day.

Foundation Work Continues
June 25, 2010

Work on the foundation and foundation walls continues as the completion of the initial concrete pours nears. Steel installation is scheduled to begin in early July.

Work is scheduled on Saturday, June 26, 2010.

There will be no work on Sunday, July 4, 2010 and Monday, July 5, 2010 in observance of Independence Day.

Project Update
June 8, 2010

Work on the foundation and walls will continue throughout the month of June with regular concrete pours as the site gets ready for the beginning of steel installation. Steel installation is anticipated to begin in early July. Prior to the steel installation a crane will be brought to the site.

Project Update
May 27, 2010

Work on the foundation continues. Pouring the foundation slabs and pouring the walls has begun. Looking ahead to late June, a crane is scheduled to be brought in as preparations are made for steel installation. The crane will be placed on Thompson Street inside the construction fence. A vehicular lane for traffic and pedestrian sidewalk will remain open at all times.

There will be no work on Monday, May 31, 2010 in observance of Memorial Day.

Project Update
May 10, 2010

Work on the foundation continues at 58 Washington Square South. There will continue to be regular concrete pours for the next few weeks. Once the foundation slabs have been poured they will begin to install steel, which is anticipated to begin in June.

Work on Saturdays will continue, but work will not begin until 9AM.

Lane Closure
May 5, 2010

This Saturday, May 8, 2010 a lane closure on West 3rd Street between LaGuardia Place and Thompson Street is scheduled from 7AM-3PM as mandated by DOT.

A traffic lane will remain open during this time for vehicular traffic and the southern sidewalk will remain open for pedestrians. There will be regular trucking activity during this time as the earth ramp on the south end of the site is removed. All efforts will be made to mitigate dust by wetting dirt before its removed from the site.

Lane Closure
April 22, 2010

A lane closure on Thompson Street is scheduled for this Saturday, April 24, 2010. A street crane will be brought in to hoist a large piece of equipment onto the north end of the site. Once work is completed all equipment will be removed. In the event there are unforeseeable circumstance that causes delays on Saturday, then this work will occur on Sunday. Every effort will be made to avoid working on Sunday.

This is mandated by DOT for the scope of work.

Temporary Lane Closure Scheduled
April 9, 2010

On Saturday, April 17 and April 24, 2010, there will be a temporary lane closure on the north side of West 3rd Street. The mandated DOT hours for this closure are from 7AM-3:30PM. They will begin mobilization each day at 7AM, but work will not begin until 9AM as permitted by DOB.

This lane closure is for specially outfitted excavator equipment to remove the existing earth ramp on the south side of the site. All equipment will be removed once the shift is completed so it will not remain on site. Additional work on Saturdays is expected to continue for the next few weeks.

Thompson Street Lane Closure
April 5, 2010

A lane closure will be in effect on Thompson Street to allow for concrete and foundation work for the new Center for Academic and Spiritual Life. The necessary permits have been obtained from DOT and enough street space remains to allow passage by emergency vehicles.

De-watering & Weekend Work
March 26, 2010

De-watering has begun on the site and will continue through the spring. There will be some additional work this Saturday, March 27, 2010 from 9AM-5PM.

Activity will increase in the next few weeks with more trucks as excavation continues in preparations to pour the foundation slabs. A lane closure on Thompson Street is anticipated in April.

Temporary Boiler Removal
March 15, 2010

This week the temporary boilers at Furman Hall and King Juan Carlos are scheduled to be removed. There will be some general construction noise associated with this activity, but it will happen during regular construction hours.

On Tuesday, March 16, 2010, there will be early morning activity at 58WSS. A large piece of equipment is being removed from the construction site. Per DOT requirements, this must be done between 4AM-6AM. We apologize for any inconveniences this may cause.

Project Update
March 8, 2010

In the upcoming weeks, concrete pours for the foundation slab are scheduled to begin. There will be cement trucks entering and exiting the site along West 3rd street during this time.

Also, beginning the week of March 8, 2010, the site will need continual de-watering. De-watering is needed to pump the water from below the ground level. This work involves a motor comparable to that of a lawnmower running on-site 24 hours a day. The equipment will be enclosed and an additional sound absorbing material will be added to mitigate the noise.

Weekend Work Scheduled
March 5, 2010

Additional work is scheduled this Saturday, March 6, 2010 from 9AM-5PM. Preparations are being made for the high temperature hot water pipe installation on the northwest corner of the site, which is time sensitive work.

Once this work is completed, we anticipate that the boilers currently located on Washington Square South will no longer be needed and can be removed.

City Board Approves Variance
February 23, 2010

The New York City Board of Standards and Appeals has approved NYU's proposed variance for its new Center for Academic and Spiritual Life, which will be built at 58 Washington Square South, at the corner of Thompson Street. Read more »

Project Update
February 19, 2010

Excavation will continue at 58WSS for the next few weeks. Once this is completed, pouring concrete for the foundation slab is scheduled to begin in March.

During this time, the site will need de-watering. De-watering — the pumping of water from below the ground level — is scheduled to begin in the next few weeks. This work involves a motor comparable to that of a lawnmower running on-site 24 hours a day and is anticipated to last for 6-8 weeks.

Saturday Work Scheduled
February 19, 2010

Additional work is scheduled this Saturday, February 20, 2010 from 9AM-5PM. Most of the work will be focused on the north end of the site as time-sensitive preparations are made for the high temperature hot water pipes. Once this work is completed we anticipate that the boilers currently located on Washington Square South will no longer be needed and will be removed.

Saturday and Monday Work Scheduled
February 12, 2010

On Saturday, February 13, 2010 and Monday, February 15, 2010, work is scheduled at the 58 Washington Square South site to continue excavation and tiebacks near the Thompson Street side of the site and chop concrete footings and foundation walls near the West 3rd Street side of the site.

Testing will also be done on the welding for the HTHW piping.

Project Update - Site De-watering to Begin
February 5, 2010

Excavation will continue at 58WSS for the next few weeks. Once this is completed, pouring concrete for the foundation slab is scheduled to begin.

During this time, the site will need de-watering. De-watering — the pumping of water from below the ground level — is scheduled to begin in the next few weeks. This work involves a motor comparable to that of a lawnmower running on-site 24 hours a day and is anticipated to last for 4-6 weeks.

Weekend Work Scheduled
February 4, 2010

Additional work is scheduled this Saturday, February 6, 2010 from 9AM-5PM. Most of the work will be focused on the north end of the site as time-sensitive preparations are made for the high temperature hot water pipes.

BSA Public Hearing
February 2, 2010

A BSA hearing is scheduled on Tuesday, February 9, 2010 to decide the variance application. More information can be found here.

Tree Removal
January 19, 2010

NYU has worked closely with the Parks Department about the 6 trees along Thompson Street. The Parks Department recommends that the 4 most northern trees be removed, which will take place later this week.

The 2 most southern trees, closest to Thompson Street, will remain protected throughout construction.

The University is aware how important trees are to the quality of life of the community so once construction is completed more trees will be planted along Thompson Street.

Asbestos Abatement Update
January 11, 2010

The schedule for the asbestos abatement has changed. The abatement is now scheduled to take place beginning Thursday, January 14, 2009 and is projected to be completed by Tuesday, January 19, 2009.

Project Update
January 8, 2010

Preparations for foundation work continue at 58WSS. In the next few weeks there will be increased activity along West 3rd Street as more soil and debris from the site are removed during excavation. The soil will be moistened prior to removal to mitigate dust. This is a common and effective technique used for this type of work.

King Juan Carlos Bridge Extension
January 8, 2010

The sidewalk bridge at King Juan Carlos (53 WSS) will be extended west on Washington Square South to Sullivan Street. It will be erected in front of the Kevorkian Center (50 WSS). The sidewalk bridge is being extended to carry the temporary piping from the temporary boiler located on Sullivan Street/WSS to KJC.

The extension of the sidewalk bridge will be erected on Tuesday, January 12, 2010 and is expected to be in place through March 2010.

BSA Public Hearing
January 8, 2010

A Board of Standards and Appeals (BSA) hearing has been set for Tuesday, January 12, 2010 at 1:30PM, 40 Rector Street, 6th Floor to address the building variance requested for 58 Washington Square South.

Asbestos Abatement
January 6, 2010

Asbestos abatement is scheduled to begin on Friday, January 8, 2009 and is projected to be completed by Tuesday, January 12, 2009. This work is weather dependent.

The University takes several mandated steps during abatement, including daily tests of air quality which are mandated by the Department of Environmental Protection (DEP). The University hires only licensed asbestos removal contractors, and adheres to rigorous DEP standards and policies for all abatement projects.

Furman Hall and Vanderbilt Hall Chilled Water Shutdown
December 21, 2009

Repairs of existing chilled water mains and the installation of utilities on the West 3rd side of the 58 Washington Square South site are scheduled to take place the week of January 4 - January 8, 2010. In order to perform this work, a chilled water shutdown is required at Furman Hall and Vanderbilt Hall

The shutdown will begin on January 4, 2010 at 7am and will be completed by January 8, 2010 at midnight.

Project Update
December 4, 2009

Excavation continues at 58 WSS. In the next few weeks preparations will begin for the shoring along the west edge of the foundation. In order to install the shoring, the contractor will pile drill several holes. This type of work will at times be loud, but this technique is much quieter than the alternative, pile driving, which is very disruptive.

Asbestos abatement is scheduled to begin on Wednesday, December 9, 2009 and is expected to be completed by December 16th unless there are unforeseeable delays as all of this work is weather dependent. The University takes several mandated steps during abatement including daily tests of air quality, which are mandated by the Department of Environmental Protection (DEP), are conducted to ensure air quality. The University hires only licensed asbestos removal contractors, and adheres to rigorous DEP standards and policies for all abatement projects.

Kimmel Hot Water & Heat Shutdown
November 20, 2009

A shutdown of the domestic hot water and heat in the Kimmel Center is scheduled for Saturday, November 21, 2009 starting at 11PM through Sunday, November 22, 2009 at 11AM.

This shutdown is required to disconnect the High Temperature Hot Water lines on the north west corner of the building, and reroute them for the 58 WSS site.

Excavation and Foundation Work
November 12, 2009

Excavation, foundation, and high temperature hot water work is scheduled to start at 58 Washington Square South the week of November 16, 2009. Work will include mobilization, followed by the start of excavation/foundation work and HTHW work.

Sidewalks will be closed along the perimeter of the site on Washington Square South, Thompson Street, and West 3rd Street. This will close a lane of traffic on WSS and one lane of parking on both Thompson Street and West 3rd Street to reroute pedestrian traffic around the construction zone.

This phase of the project is scheduled to take approximately six (6) months.

Pre-construction Meeting Notes
September 29, 2009

On Wednesday, September 23, 2009 there was a pre-construction meeting with the community regarding the 58 Washington Square South project.

As discussed, the mobilization of the site has begun. The scope of work includes the installation of the construction fence along the perimeter, a protective pedestrian walkway, the installation of a sidewalk bridge on WSS that will have the construction office on top of it and another sidewalk bridge along a small part of West 3rd street.

There will be a loss of parking along the west side of Thompson Street and the North side of West 3rd Street during this project. Excavation and work on the foundation will begin over the next few weeks and continue through Spring 2010. Once this scope of work is completed, work will begin on the construction of the building. The project is expected to be completed in Spring 2012.

Some of the concerns that were brought to the University's attention included:

  1. Vibrations - There will be vibration monitoring of the site and the University will take every precaution necessary to ensure not only the safety of our site, but the surrounding community as well.
  2. Dust Mitigation - The site will be misted before and during work to mitigate dust.
  3. Rodent Mitigation - Traps will be set and we will monitor the situation throughout the project.