Washington Square Village Water Tank Replacement


New rooftop water tanks are required at Washington Square Village buildings 1, 2, 3, and 4.  

 

Information for Neighbors

 

Project Timeline
 

  • The project will start on or around the week of April 15 and be complete by May 31, 2014.
  • Tanks on buildings WSV 4 and 3 will be replaced first. When this construction is completed (estimated time of one month), the process will begin for WSV 1 and 2.

Scope of Work

 

  • Replacement begins with demolition of the existing water tanks, followed by the installation of new tanks.
  • The final step in demolition involves decommissioning the existing tanks, a process which will suspend water service for approximately a 12 hour period.
  • Once the precise date of the tank replacement is scheduled, we will post notifications in building lobbies. We will give at least 48 hours notice.
  • Hoists will be installed on the garden-facing facades of WSV 4 from mid-April into May, and on WSV 1 throughout May.
  • When the materials are being delivered or removed via the hoist, traffic along the WSV driveways may be temporarily suspended and/or rerouted to accommodate the lifting.

Updates and Announcements

 

Construction Update, July 2, 2014

1 Washington Square Village is scheduled to undergo a complete hot and cold water shutdown on Wednesday, July 9, from 9:00 am – 9:00 pm. We apologize for this inconvenience and thank you for your patience during the installation.

Construction Update, June 24, 2014

Roof work and abatement at WSV 3 are scheduled to begin this week and continue through the end of the summer. A roof hosit will be installed after abatement has been completed (July) followed by masonry repairs and roof replacement. Work hours are 7:00 am - 5:00 pm.

Construction Update, June 19, 2014

4 Washington Square Village is scheduled to undergo a complete hot and cold water shutdown on Monday, June 30, from 9:00am – 9:00pm. We apologize for this inconvenience and thank you for your patience during the installation.

Construction Update, May 14, 2014

Rooftop rigging is scheduled for installation on the northeast face of 4WSV on May 14. Materials deliveries will begin once installation is complete.

Construction Update, April 14, 2014

Project details have been established and work has begun.

mews

Work hours

 

  • Monday - Friday,
    7:00 am - 5:00 pm
  • In instances where night or weekend work is required, community members will be given advanced notice.

Latest News

 

July 2 2014

1 Washington Square Village is scheduled to undergo a complete hot and cold water shutdown on Wednesday, July 9, from 9:00 am – 9:00 pm. We apologize for this inconvenience and thank you for your patience during the installation.

Read more »