Sullivan Street Sidewalk Restoration


NYU will rehabilitate sections of the sidewalk surrounding Vanderbilt Hall and Furman Hall (245 Sullivan Street and 40 Washington Square South). 

 

Information for Neighbors

 

Project Timeline
 

  • The project is scheduled to start in June and continue through August, 2014.
  • Protective sidewalk sheds are slated to be erected in early June.
  • Sidewalk demolition is scheduled to last through June.   

Scope of Work

 

  • The rehabilitation process begins with demolition, followed by waterproofing of the below-grade structure, followed by the pouring of new surface concrete.
  • Sidewalk repairs will take place in three locations: on each side of the street in front of 245 Sullivan Street, and on the north side of West 3rd Street just west of Sullivan Street (behind 40 Washington Square South).
  • Enclosed sidewalk sheds will be built to reduce sound and dust.

Updates and Announcements

 

Construction Update, August 14, 2014

Work at Vanderbilt Hall is scheduled to finish the week of August 18. Waterproofing on Sullivan Street and soil removal on West 3rd Street have been scheduled for Saturday, August 16 and Saturday, August 23.

Construction Update, August 11, 2014

Work at Furman Hall has been completed. Work at Vanderbilt Hall is scheduled to finish the week of August 18.

Construction Update, July 14, 2014

On Saturday, July 19, the construction fence will be removed from the southern half of the sidewalk at Furman Hall, and work will take place at the Vanderbilt Hall sidewalk on Sullivan Street.

Construction Update, June 6, 2014

Project details have been established and work has begun.


Stay Connected

 

Contact Us

Construction at NYU Langone

Sign Up for Updates

  • Want to receive updates about NYU construction projects in your neighborhood? Fill out our online form to receive word if a construction project happens nearby. Join the list »
Furman Hall

Work hours

 

  • Monday - Friday,
    8:00 am - 5:00 pm
  • Jackhammer work is to begin no earlier than 9:00 am.
  • In instances where night or weekend work is required, community members will be given advanced notice.

Latest News

 

August 14 2014

Waterproofing on Sullivan Street and soil removal on West 3rd Street have been scheduled for Saturday, August 16 and Saturday, August 23.

Read more »