Meyer Building Renovations, 4 Washington Place


NYU will be renovating the 1st, 4th, and 7th floor of the Meyer Building, and installing new rooftop equipment. This project includes internal demolition, abatement, renovation work, and window work.

 

Information for Neighbors

 

Project Timeline
 

  • The project is scheduled to begin in December, 2013, and continue through the summer of 2015.
  • Demolition, abatement, and debris removal will continue through spring, 2015.
  • Construction and renovation work will continue for the duration of the project.

Scope of Work

 

  • The project includes renovations on the 1st, 4th, and 7th floor of the Meyer Building, and the installation of rooftop equipment. Renovations will include internal demolition, abatement, and renovation work. Broadway-facing windows will be renovated on the 4th and 7th floors.
  • The majority of the work will be interior.
  • Dumpster truck(s) will be located on Mercer Street for debris removal.
  • Periodic deliveries will continue through summer 2015.
  • There will be periodic internal asbestos abatement, which will require the use of an asbestos abatement truck on Washington Place between Broadway and Mercer.

Updates and Announcements

 

Construction Update, April 25 2014

Internal work, debris removals, and periodic deliveries have been scheduled to continue through summer 2015.

Construction Update, April 4 2014

A concrete truck will be staged Friday, April 11th, 8:00 am-5:00 pm, on the corner of Mercer Street and Washington Place.

Construction Update, March 27 2014

A packer truck will be staged on Mercer for debris removal on March 27th and March 28th. A concrete truck will be in use on Friday, April 4th between 8:00 am and 5:00 pm on the corner of Mercer Street and Washington Place.

Construction Update, March 21 2014

The concrete pour originally scheduled for Saturday, March 22 has been rescheduled to Friday, March 28, from 8:00 am to 5:00 pm. The concrete truck will stage on Mercer Street.

Construction Update, March 12 2014

A concrete truck will be in use Saturday, March 22 between 9:00 am and 5:00 pm on the corner of Mercer Street and Washington Place.

Construction Update, March 6 2014

Abatement work continues. Two abatement trucks are required for asbestos removal. Work hours will be 7:00 pm to 1:00 am, Monday through Saturday. Information about NYU's asbestos abatement protocols can be found on our FAQ page.

Construction Update, February 20 2014

Abatement has been re-scheduled through mid-March. Two abatement trucks are required for asbestos removal. Work hours will be 7:00 pm to 1:00 am. Information about NYU's asbestos abatement protocols can be found on our FAQ page.

Construction Update, January 28 2014

Abatement is scheduled to start the week of February 3rd. Abatement will take approximately three weeks to complete. Two abatement trucks are required for asbestos removal. Work hours will be 7:00 pm to 1:00 am. Information about NYU's asbestos abatement protocols can be found on our FAQ page.

Construction Update, January 13 2014

Demolition work has been rescheduled to start the week of January 20th.

Construction Update, December 20

Project details have been established, and work has begun.

Meyer Building

Work hours

 

  • Monday - Friday
    7:00 am - 5:00 pm
  • Saturday
    9:00 am - 5:00 pm
  • In instances where additional night or weekend work is required, community members will be given advanced notice.

Latest News


April 4 2014

Internal work, debris removals, and periodic deliveries have been scheduled to continue through summer 2015.  

Read more »