Welcome to the New York University Construction Website. Here you will find useful information about the University's construction projects, including project descriptions, announcements, and answers to frequently asked questions. For details click on pins in the interactive map or visit current projects »


Spotlight on Current Projects


Stay Connected

 

General Inquiries

Sign Up for Updates

  • Want to receive updates about NYU construction projects in your neighborhood? Fill out our online form to receive word if a construction project happens nearby. Join the list »

Emergency Repairs


75 Third Avenue
Water Main Break

August 13, 2014
Due to a Department of Transportation summer embargo on weekday street work, repairs are scheduled for Saturday, August 16, 2:00 pm - 10:00 pm, and Sunday, August 17, 9:00 am - 6:00 pm. Work will involve approximately 12' x 10' of surface excavation.


Announcements


18 Waverly Place

August 13, 2014
Construction supports are scheduled to be dismantled: pipe scaffolding in the 15 Washington Place courtyard on Friday, August 15 and Monday, August 18, and sidewalk bridging on Waverly Place from August 25. Read more »


14-16 Washington Pl

August 13, 2014
Internal construction and catch basin repairs are scheduled to finish this week, weather permitting. Permit approvals have delayed courtyard repairs. The laundry room will be closed Thursday, August 14, 8:00 am - 4:00 pm.


5 University Place
Weinstein Hall Work

August 11, 2014
Work is scheduled to finish by the end of August. The sidewalk shed must remain in place. Read more »


42 Washington Mews

August 11, 2014
Work is scheduled to be completed the week of August 25th, with sidewalk bridging and pipe scaffolding to be dismantled thereafter. Read more »


For previous updates, explore individual project pages.